Erecting shelter frames

IMG_1694
Two frames up-six to go

Today, with the help of my mate Simon and his crane, we started erecting the frames. Slow going at first, and it took all morning to erect two frames. I sent Simon home at lunch, as I realised I had to re-think the process, and did not want to waste his time. I decided to prepare the remaining frames, pre-screwing the connecting saddles and pre-drilling locating holes to save crane time. The photo shows the assembled frames yet to be erected.